Table 1 : Indian Railways : Value of Assets (as on 31st
March) |
|
|
|
|
|
|
(Rs.crore) |
1.Capaital-at-Charge
(comprising loan account) |
|
|
|
|
|
|
|
2005 |
2000 |
1992 |
1984 |
1977 |
Land |
|
1726.65 |
651.86 |
333.56 |
111.90 |
76.32 |
Structural
Engineering Works |
26155.20 |
13771.77 |
8004.67 |
3225.08 |
1955.57 |
1 |
Stations and Offices |
2613.83 |
771.95 |
524.01 |
193.89 |
103.10 |
2 |
Workshop and Stores Buildings |
1707.27 |
816.00 |
518.84 |
261.51 |
62.04 |
3 |
Residential Buildings |
1744.78 |
912.08 |
606.82 |
193.71 |
96.21 |
4 |
Tracks (formation+permanent way materials+Bridges) |
20089.32 |
11271.74 |
6355.00 |
2575.97 |
1694.22 |
Rolling Stock |
9205.50 |
6787.14 |
4155.67 |
3023.37 |
1900.20 |
1 |
Locomotives and Spare Boilers |
5095.39 |
3312.80 |
1647.75 |
1045.76 |
560.87 |
2 |
Carriages including Rail Cars and E.M.U stcok |
2250.34 |
1595.93 |
1020.79 |
811.94 |
542.81 |
3 |
Wagons |
1848.00 |
1874.94 |
1483.08 |
1169.35 |
792.98 |
4 |
Ferries |
2.03 |
2.18 |
3.22 |
3.25 |
3.54 |
5 |
Rail-Cum-Road Services |
9.74 |
1.29 |
0.83 |
-6.93 |
- |
Machinery and
Plant |
8713.65 |
6452.76 |
3493.46 |
760.02 |
218.77 |
Inventories,etc. |
3428.87 |
1285.53 |
1246.08 |
437.80 |
206.38 |
Investment in
Shares |
1615.15 |
706.25 |
479.02 |
9.63 |
58.23 |
Total |
|
50845.02 |
29655.31 |
17712.46 |
7567.80 |
4533.70 |
2.Block Assets
( Capital-at-Charge and also assets created out of Development fund as also
the improve- |
|
ment element in assets created out of
Depreciation reserve fund and ACSPF as shown in block account). |
|
|
|
2005 |
2000 |
1992 |
1984 |
1977 |
Land |
|
1964.25 |
829.62 |
360.32 |
111.91 |
76.32 |
Structural
Engineering Works |
57705.30 |
32191.84 |
12629.29 |
4397.89 |
2596.57 |
1 |
Stations and Offices |
5182.45 |
2342.61 |
1038.93 |
379.76 |
213.93 |
2 |
Workshop and Stores Buildings |
2595.39 |
1466.55 |
676.71 |
324.49 |
103.50 |
3 |
Residential Buildings |
3274.78 |
1694.05 |
937.96 |
386.55 |
251.14 |
4 |
Tracks (formation+permanent way materials+Bridges) |
46652.68 |
26688.63 |
9975.69 |
3307.09 |
2028.00 |
Rolling Stock |
16739.42 |
11761.15 |
5121.63 |
3257.19 |
2032.04 |
1 |
Locomotives and Spare Boilers |
8666.25 |
5569.16 |
2112.02 |
1146.70 |
616.83 |
2 |
Carriages including Rail Cars and E.M.U stcok |
4661.68 |
3333.54 |
1360.34 |
864.71 |
584.18 |
3 |
Wagons |
3320.89 |
2850.94 |
1644.37 |
1248.80 |
826.83 |
4 |
Ferries |
3.02 |
3.00 |
3.88 |
3.91 |
4.20 |
5 |
RAIL-Cum-Road Services |
87.58 |
4.51 |
1.02 |
-6.93 |
0 |
Machinery and
Plant |
16102.44 |
10309.35 |
4354.08 |
910.74 |
266.35 |
Inventories,etc. |
3441.59 |
1798.36 |
1367.04 |
438.22 |
206.61 |
Investment in
Shares |
1635.39 |
726.32 |
479.87 |
9.64 |
58.44 |
Total |
|
97588.39 |
57616.64 |
24312.23 |
9125.59 |
4533.70 |
Physical
Assets |
|
|
|
|
|
1 |
Number of Stations |
7133 |
6867 |
7116 |
7065 |
7057 |
2 |
Number of Bridges |
121295 |
122032 |
116000 |
112976 |
111309 |
|
of which: Major |
9682 |
10764 |
10283 |
9506 |
9224 |
3 |
Number of Level Crossing |
35132 |
38659 |
38932 |
41518 |
40638 |
|
of which: Manned |
16642 |
16313 |
15775 |
15059 |
14208 |
4 |
Land Owned by Railways in Lakh Hectares |
4.23 |
4.20 |
4.19 |
- |
- |
|
of which: Track & Structures |
3.10 |
3.34 |
2.97 |
- |
- |
|
Vacant Land |
0.43 |
0.25 |
0.61 |
- |
- |
5 |
Loco Shed in Operation |
98 |
104 |
207 |
275 |
- |
6 |
Repair Depots |
296 |
324 |
409 |
426 |
- |
7 |
Work Shed |
45 |
44 |
46 |
49 |
46 |
Notes: |
In 1977 total includes an amount of Rs.118.23
crores under miscellaneous account |
|
|
|
|
Land, Formation under tracks,
inventories,investment in shares are non wasting assets. |
|
|
|
Block
account forms an annexure to
appropriation accounts for the Indian Railways indicates the total including
value of |
|
assets
financed from the development fund, accident compensation, safety and
passenger amenities fund and revenue |
|
as also the improvement element of the cost of
assets financed from the depreciation resefrve fund. |
|
|
Total excludes minor assets financed from
revenue as its replacement is financed from the current revenue. |
|
Source: |
GOI(2006),
Explanatory Memorandum on the Railway Budget for 2006-07, Ministry of
Railways |
|
|
|
(Railway Board), February and earlier issues. |
|
|
|
|
|
|
|
|
|
|
|
|